How to Plan the Order of Work in a Home Renovation

The order of work in a home renovation is planned so that one job does not damage another that is already finished. In our projects, work proceeds in this order: design first, then strip-out, then services, then surfaces and floor coverings, and finally installation. If the order is wrong, a freshly painted wall is opened again for pipework, or a newly laid floor is damaged by the jobs that follow.

In this article, we go through that order step by step. This general flow is planned according to the scope of the work and the conditions on site; the details and scope become clear after the site visit.

1. Site visit, measurements and design decisions

The work starts on paper, not on site. During the site visit, we see the space, take measurements and listen to what you need. We then send the proposal form listing the items of work.

Socket and lighting points, the kitchen and bathroom layout and the position of the cabinets should be settled before implementation begins, because these decisions determine where the pipework and wiring will run. In the design stage, we show the space in 3D visuals and present the materials and lighting for your approval. In the Eryaman Ay Yıldız Sitesi project, the concealed LED strip in the living room runs around both the TV wall and the ceiling; the wiring for this kind of lighting is planned before the walls and ceiling are closed.

2. Strip-out and preparation

The floor covering to be renewed, old cabinets, tiles to be replaced and sections to be removed are stripped out. Surfaces and belongings that will stay are protected at this stage. After strip-out, the real condition of the walls and floor can be seen; if necessary, the plan is updated accordingly.

3. Services: plumbing and electrical work

Water, waste water, heating and electrical lines stay inside the walls and floor. That is why they are generally completed before the surfaces are closed. If there is underfloor heating, it is installed before the floor covering. In the Panorama Beytepe Villas project, we enclosed two open terraces and added them to the living space. Underfloor heating was also within the scope of work in this project.

In wet areas, waterproofing is done before the tiles.

4. Surfaces and floor coverings

After the services, the next jobs are mostly plastering, suspended ceilings and wall corrections. Tiles are then laid in the bathroom and kitchen. The order of painting and floor covering depends on the type of floor; delicate floors such as parquet are, in most projects, laid after the dusty work is finished. In the Ay Yıldız project, we renovated the bathroom with a shower enclosure and patterned tiles.

5. Furniture measurements and production

Bespoke kitchens, wardrobes and cabinets are made in the workshop. We take the final measurements for bespoke furniture once the rough work is finished, after the floor coverings. We run production alongside the site work and make the furniture in our own Noyer Home workshop.

6. Installation, final coat of paint and handover

Cabinets, doors, worktops and built-in appliances are fitted. Light fittings, sockets and sanitaryware are installed. The timing of the final coat of paint and touch-ups depends on the project; the aim is that installation does not damage a finished surface. After the final clean, we hand over the space ready for use, and we walk through it with you at handover. We provide a 1-year company warranty on our projects; our site managers assess your requests after handover.

Can a home be renovated while you are living in it?

It can, but the order of work is then divided into sections and the areas in use are protected. Working while the home is empty simplifies the sequence. In the Panorama Beytepe project, we carried out the implementation while the villa was empty. We assess together which option is suitable during the site visit, according to the scope of the work.

You can read the details of the scope on our turnkey renovation page, and the factors that affect the budget in our article on what determines the cost of a renovation.

Frequently asked questions

The two belong to the same stage: surfaces and floor coverings are done after the services and before installation. The order between them depends on the type of floor and the scope of the work; the aim is that later work does not damage a finished surface.

The layout is decided in the design stage. We take the final production measurements once the rough work is finished, after the floor coverings.

In turnkey work, our own team manages the site. You do not coordinate the tradespeople, the materials or the order of work; you have a single point of contact.

If you would like to plan the renovation of your home together, contact us for a free site visit.

Book a free site visit ↗Browse our projects →

Let's talk about your next space.

Tell us about your project and let's add value to your space together. Interior architecture and turnkey fit-out in Ankara and the surrounding area.

Tell Us About Your Project →
Haymana Villa, exterior with pool (3D visualisation)
Creative Mimari© 2026 Creative Mimari · 10+ years and 200+ completed projects in Ankara